Homebuyers Shouldn’t Face Endless Wait for Possession, NCDRC Rules Against Ansal Properties for Delays

Order Date: 29th July 2024
Order Name: S.K. Rathore vs Ansal Properties and Infrastructure Ltd. and Anr. (and connected matters)
Case No.: First Appeal No. 44 of 2018

The National Consumer Disputes Redressal Commission (NCDRC) has held Ansal Properties and Infrastructure Ltd. accountable for failing to deliver a flat on time despite receiving regular payments. The bench, led by Subhash Chandra (Presiding Member), ruled in favor of the complainant, who had booked a flat in the ‘Celebrity Meadows’ project in Sushant Golf City, Lucknow.

Key Details:

Background:

  • The complainant booked a flat priced at Rs. 35,35,165/- and paid an initial amount of Rs. 1,82,000/- in 2010.
  • The possession was promised within 36 months from the approval of building plans, subject to certain conditions.
  • By October 2015, the complainant had paid Rs. 32,38,255/- but did not receive possession by the expected date in October 2013.
  • Additional payments were made upon demand, yet the flat was not delivered.

    State Commission Order:

  • The State Consumer Disputes Redressal Commission, Uttar Pradesh, initially directed Ansal Properties to complete the flat and hand over possession within three months upon receiving the balance amount.
  • Ansal Properties was also ordered to pay Rs. 10,000/- as litigation costs.

    Appeals:

  • Dissatisfied, the complainant appealed to the NCDRC for higher compensation.
  • Ansal Properties also appealed, seeking to overturn the State Commission’s order.

    NCDRC Observations:

  • Delay in Project Completion: Ansal Properties admitted the project was incomplete and lacked necessary certificates even after ten years.
  • Legal Precedents: The NCDRC cited multiple Supreme Court judgments, emphasizing that buyers should not be forced to accept delayed possession and are entitled to refunds with compensation or interest.
  • Force Majeure Argument: Ansal Properties’ claim that delays were due to uncontrollable factors was unsupported by evidence and rejected.
  • IBC Proceedings: Ansal Properties’ reliance on an unrelated insolvency order was dismissed as irrelevant.

    Final Decision:

  • Refund with Interest: The NCDRC directed Ansal Properties to refund all amounts paid by the complainant with 9% interest per annum from the respective deposit dates.
  • Litigation Costs: Ansal Properties was also ordered to pay Rs. 50,000/- as litigation costs.

    Takeaway:

    This judgment reinforces that property developers must adhere to promised timelines, and buyers are entitled to refunds with compensation if there are undue delays. It serves as a reminder to always verify the credibility and track record of developers before making significant financial commitments.

Leave a Reply

Your email address will not be published. Required fields are marked *

×

Hello!

Click one of our contacts below to chat on WhatsApp

×